MWANZA: VICE-PRESIDENT Deogratius Ndejembi has ordered Mwanza Regional Commissioner, CP Salum Hamduni, to take legal action against the contractor if the project remains unfinished after the extended deadline.
The directive followed an inspection of the project in Butimba Ward, Nyamagana District, which includes the construction of a 100-metre access road.
The project, awarded to Comfix and Engineering Co Ltd, is significantly behind schedule, with progress standing at just 22 per cent against the expected 88 per cent.
Concerned by the slow pace of work, Mr Ndejembi questioned whether the contractor could realistically complete the project by February 8, 2027, given the current level of progress.
He insisted that the contractor must fulfil its contractual obligations, warning that public funds invested in the project cannot be allowed to go to waste.
“I expect the project to be completed by February 8, and you have committed yourself in writing. If that date arrives and there is no work, Regional Commissioner, I am usually reluctant to order people’s detention, but when public funds are misused, there is no alternative but to take tough action to serve as a lesson to others. That authority rests with you, and if the work is not completed, appropriate action must be take,” he said.
He also questioned how the 800 traders initially expected to benefit from the facility would be accommodated following a reduction in the number of fish selling stalls from 1,200 to 400.
“This delay denies small scale fish traders an opportunity to conduct business and earn income. You need to complete the facility within the agreed timeframe,” he said.
Dr Ndejembi said the government had prioritised local contractors to strengthen their capacity to undertake major development projects.
However, he cautioned that delays by some domestic contractors risked undermining the government’s confidence in other local companies seeking opportunities to execute public projects.
Explaining the reasons for the delay, Mwanza City Council Director, Advocate Kiomoni Kibamba, said construction had been suspended for nine months to allow a review of the project design.
He explained that the initial design required deep foundation piles, but the works had not been included in the contract’s bill of quantities and cost estimates.
Following the discovery of the omission, the estimated project cost rose to 22bn/-, exceeding the funds allocated for the project.
Mr Kibamba said the construction plan was subsequently revised to align with the available budget.
Under the initial design, the market was expected to accommodate 1,200 fish selling stalls and 177 warehouses.
However, the revised plan provides for 400 stalls and 56 shops.